Client Challenge:

As a part of their Permian basin gathering expansion, the Client sought to construct a major gas processing plant in West Texas, south of Midland. Facility capabilities include a capacity of 70+ MMcf/d and an NGL output of more than 11,000 barrels.

The TorcSill Solution:

The Client sought the assistance of TorcSill in the design and construction of foundations to support major equipment on site, including process towers, compressor canopy, vessels, pumps and other skidded equipment. In addition to providing a schedule savings of three months over concrete foundations, TorcSill completed the work with a perfect safety record.

  • Project: West Texas Gas Plant
  • Number of Piles: 789
  • Project Type: Midstream Gas Processing Plant